2015 FITZROY Port Hedland

2 separate shore ends. Double 44km cable installation with simultaneous laying and trenching (both cables in the same trench) and surface lay with a minimum 5m separation between both cables. Installation of articulated pipes.

Location : Port Hedland / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable
Length (km): 2 x 44
Water depth (m) : up to 17 m
Vessel : Barge
Burial system : TM04 (trenching) + EBJ (jetting)
Burial depth (m) : 0.5
Weight (kg/m) : 3.5
Diameter : 35

Other projects

  • 2014 WINTERSHALL

    Provision of personnel and equipment to carry out the post burial of 1 umbilical between 2 offshore platforms.
    Burial system : ROVJET806 (jetting)
    Plus d’infos
  • 2007 ATLAS OFFSHORE

    FO cable shore ends – Post lay burial
    Burial system : EBJ 04 (jetting)
    Plus d’infos
  • 2023 2 AFRICA SOUTH AFRICA

    1 x Direct landing in Port Elizabeth, shell installation, post beaching, clamp installation. Installation of grounding system
    Burial system :
    Plus d’infos