Home » Projets » 2016 MARJAN GOSP

2016 MARJAN GOSP

Provision of personnel and equipment to carry out the post-lay burial of one 115 kV power cable.

Location : Saudi Arabia
Client : Mc Dermott Arabia Company Ltd

Product : Power Cable
Length (km): 31 km
Water depth (m) : 0 to 30
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1
Weight (kg/m) : 83
Diameter : 214 mm