2017 LTAII

Provision of personnel and equipment to carry out trenching services on four 115 kV submarine power cables on Berri field + one 115 kV and five 15 kV submarine power cables on Safaniya field.

Location : Berri and Safaniya fields – Saudi Arabia
Client : Mc Dermott Arabia Company Ltd

Product : Power Cable
Length (km): 16 + 15 km
Water depth (m) : 0 to 6
Vessel : Barge
Burial system : TM03 + TM04 (trenchers)
Burial depth (m) : 1
Weight (kg/m) : up to 83
Diameter (mm) : up to 218