Home » Projets » 2020 Dunant

2020 Dunant

Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.

Location : Saint Hilaire de Riez / France
Client : Subcom

Product : Fibre optic cable 
Length (km): 5
Water depth (m) : up to 15 m
Vessel : DP Vessel
Burial system : TO Mobile NV (jetting)
Burial depth (m) :

Other projects

  • 2014 BUTENDIEK

    Provision of personnel and equipment to carry out the post burial of 86 infield power cables.
    Burial system : ROVJET806 (jetting)
    Plus d’infos
  • 2015 WASIT

    Provision of personnel and equipment to carry out the post lay trenching of a 15 kV power composite cable.
    Burial system : TM04 (trenching)
    Plus d’infos
  • 2012 CAT – THAÏLAND

    2 separate pre-laid shore ends at Sri Racha and Songkhla + Installation of articulated pipes.
    Burial system : EBJ 04 + ESV12 (jetting)
    Plus d’infos