Home » Projets » 2021 AMITIE

2021 AMITIE

Separate shore ends in La Grigne. HDD Pulling, Laying and burial of 2.3 km of fibre optic cable.

Place: La Grigne (France)
Client : Alcatel Submarine Networks (ASN)

Product : fibre optic cable
Length:2.3 km
Depth: Up to 15 m
Ship: Barge
Burial system: Mass Flow Excavation
Burial depth: 1 m

Period: Sept 2021

Other projects

  • 2022 GRACE HOPPER

    Separate landing in a directional borehole. Simultaneous installation and beaming with mechanical trencher
    Burial system :
    Plus d’infos
  • 2020 HAVHINGSTEN System

    Laying and burial of 1 fiber optic cable in Blackpool (UK) and 2 fiber optic cables in Houstrup (Denmark).
    Burial system : TO Mobile NV
    Plus d’infos
  • 2023 YUNLIN

    Assistance to laying
    Burial system :
    Plus d’infos