Home » Projets » 2025 MARJAN GOSP 4

2025 MARJAN GOSP 4

Supply of personnel and trenching services for two separate 230 kV composite submarine cable burial services on the Marjan field as part of the Marjan Oil-Gas Separation Plant No. 4 (MRJN GOSP 4) development project.

Location: Kingdom of Saudi Arabia
Customer: McDERMOTT

Length (km): 2 x 31 km
Water depth (m): 7.5 m
Vessel: DP barge
Trenching system: TMO 3 Trencher
Trenching depth (m): 1
Product : Power cable
cable type: 230kV, 3C x 1000mm²+ 72 FO
OD 239mm

Other projects

  • 2022 MAPUTO

    Separate landing in Maputo. Laying and post-wiring of 42 km of fiber-optic cable
    Burial system :
    Plus d’infos
  • 2013 LONDON ARRAY

    Provision of personnel and equipment to carry out the post burial of 54 infield cables, some in very shallow water.
    Burial system : ROVJET605 (jetting)
    Plus d’infos