Home » Projets » 2023 GHANA

2023 GHANA

Separate landing in Accra. Laying and post-wiring of 4.9 km of fiber optic cable

Location: Accra Ghana
Customer : ALCATEL SUBMARINE NETWORKS

Length (km): 4.9 km
Water depth (m) :
Vessel: NORA B
Beam system: TO MOBILE / NV
Beam depth (m): 2.0 m
Product : Fiber optic cable
cable type: ø37mm

Other projects

  • 2017 LTAII

    Provision of personnel and equipment to carry out trebsching services on a total of 10 submarine power cables.
    Burial system : TM03 + TM04 (trenchers)
    Plus d’infos
  • 2020 Dunant

    Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.
    Burial system : TO Mobile (jetting)
    Plus d’infos
  • 2015 ABU ALI

    Provision of personnel and equipment to carry out the post lay trenching of a 15 kV power composite cable.
    Burial system : TM03 (trenching)
    Plus d’infos