Home » Projets » 2008 DELMA

2008 DELMA

Post trenching of 2 power cables between Shuwaihat (mainland) and Delma Island. Installation of articulated pipes.

Location : Delma Island (UAE)
Client : NEXANS Norway

Length (km): 85
Water depth (m) : 35
Vessel : Barge
Burial system : TM04 (Trencher)
Burial depth (m) : 1
Product : Power Cable
Weight (kg/m) : 55
Diameter : 194 mm