Home » Projets » 2008 PERENCO RDC

2008 PERENCO RDC

Cable laying and burial between mainland and platforms. Barge operating for pipe laying + special liftings + J-tube pullin.

Location : Democratic Republic of the Congo
Client : PERENCO

Length (km): 22
Water depth (m) : 20
Vessel : Barge
Burial system : EBJ 04 (jetting)
Burial depth (m) : 0,8
Product : Power Cable
Weight (kg/m) : 7
Diameter : 96 mm