Home » Projets » 2008 PERENCO RDC

2008 PERENCO RDC

Cable laying and burial between mainland and platforms. Barge operating for pipe laying + special liftings + J-tube pullin.

Location : Democratic Republic of the Congo
Client : PERENCO

Length (km): 22
Water depth (m) : 20
Vessel : Barge
Burial system : EBJ 04 (jetting)
Burial depth (m) : 0,8
Product : Power Cable
Weight (kg/m) : 7
Diameter : 96 mm

Other projects

  • 2015 FITZROY Port Hedland

    2 separate shore ends. Double 44km cable installation with simultaneous laying and trenching and then surface lay.
    Burial system : TM04 (trenching) + EBJ (jetting)
    Plus d’infos
  • 2015 ILE D’YEU

    Surface laying of 2 sections of power cable YEU3 and YEU4.
    Burial system : N.A.
    Plus d’infos
  • 2000 PEC / LEVEL 3/ FLUTE

    PLIB works on telecom fibre optic cable crossings.
    Burial system : MED 1: Dredge pump / jetting tool
    Plus d’infos