2008 PERENCO RDC

Cable laying and burial between mainland and platforms. Barge operating for pipe laying + special liftings + J-tube pullin.

Location : Democratic Republic of the Congo
Client : PERENCO

Length (km): 22
Water depth (m) : 20
Vessel : Barge
Burial system : EBJ 04 (jetting)
Burial depth (m) : 0,8
Product : Power Cable
Weight (kg/m) : 7
Diameter : 96 mm

Other projects

  • 2022 2 AFRICA Spain

    1 x Direct landing in Barcelona, shell installation and post-burial. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2005 PERENCO Gabon

    Mainland to platforms. Surface lay + J-tube Pull-In
    Burial system : N.A.
    Plus d’infos
  • 2011 ACE – SENEGAL

    2 direct FO shore-ends in Dakar (Senegal). Protection of cable (burial, articulated pipes, grout bags)
    Burial system : EBJ (Jetting)