Provision of personnel and equipment to carry out the post burial of 86 infield power cables.

Location : AMRUMBANK Offshore Windfarm / German North Sea
Client : Siem Offshore Contractors

Product : Power Cable 
Length (km): 75
Water depth (m) : up to 24 m
Vessel : DP Vessel
Burial system : ROVJET810 (jetting)
Burial depth (m) : 1.6
Weight (kg/m) : up to 36 kg/m
Diameter : up to 145 mm