2015 FITZROY Port Hedland

2 separate shore ends. Double 44km cable installation with simultaneous laying and trenching (both cables in the same trench) and surface lay with a minimum 5m separation between both cables. Installation of articulated pipes.

Location : Port Hedland / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable
Length (km): 2 x 44
Water depth (m) : up to 17 m
Vessel : Barge
Burial system : TM04 (trenching) + EBJ (jetting)
Burial depth (m) : 0.5
Weight (kg/m) : 3.5
Diameter : 35