Home » Projets » 2017 BEATRICE OWF

2017 BEATRICE OWF

Provision of personnel and equipment to carry out the post lay burial of 56 infield power cables.

Location : Beatrice Offshore Windfarm / North sea 
Client : Seaway Offshore Cables

Product : Power Cable 
Length (km): 93
Water depth (m) : up to 55 m
Vessel : DP Vessel
Burial system : ROVJET1210 (jetting)
Burial depth (m) : 0.8

Other projects

  • 2018 ASC Indonesia

    Post lay inspection and burial of 41 km of fibre optic cable.
    Burial system : ROVJET 605 (jetting)
    Plus d’infos
  • 2023 BLUE GENOA

    2 x Direct landings at Genoa in a directional borehole. Shell installation
    Burial system :
    Plus d’infos
  • 2001 ULYSSE

    Recover of existing cable (5 km), simultaneous lay and burial work (ESV12), PLIB work of joints (MED 1 and diver pump).
    Burial system : MED1 (Dredge pump) – ESV12 (Plough)
    Plus d’infos