Home » Projets » 2013 VISCAS SIR BANYAS

2013 VISCAS SIR BANYAS

Lay and burial of 2×13 km of 132kV power cable + 2x13km FO cable between Shuweihat and SIR BANIYAS (mainland to Island)

Location : Sir Banyas Island (UAE)
Client : VISCAS
Length (km): 2 x 13
Water depth  (m) : 0 to 35
Vessel : Barge
Burial system : TM04 (trencher)
Burial Depth (m) : 1
Product : power cable + FO cable
Weight (kg/m) : 55
Diameter : 226 mm

Other projects

  • 2006 THAILAND KHO SAMUI

    Shore ends/Mainland to island/Laying and burial of 115 kV power cable
    Burial system : TJV05 – TJV08 (Jetting)
    Plus d’infos
  • 2021 YUNLIN OWF

    Provision of personnel and equipment to carry out the post lay burial of infield array cables.
    Burial system :
    Plus d’infos
  • 2015 FITZROY Port Hedland

    2 separate shore ends. Double 44km cable installation with simultaneous laying and trenching and then surface lay.
    Burial system : TM04 (trenching) + EBJ (jetting)
    Plus d’infos