Home » Projets » 2014 PERENCO RDC CONGO

2014 PERENCO RDC CONGO

Laying of 43 km of power cable between mainland / platforms and platforms. Post burial of 22.5 km of cable. I-tube and Jtube pulling.
Location : Democratic Republic of the Congo – Congo
Client : PERENCO
Length (km): 43
Water depth (m) : 0 to 100
Vessel : Barge
Burial system : ROVJET 806 + EBJ : jetting
Burial depth (m) : 1
Product : Power Cable
Weight (kg/m) : 19
Diameter : 105 mm

Other projects

  • 2024 2 AFRICA PEARLS

    1 x Direct landing in Salalah, shell installation, post-sinking. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2018 INDIGO

    Post lay inspection and burial of 39 km of fibre optic cable.
    Burial system : ROVJET 605 (jetting)
    Plus d’infos
  • 2013 VISCAS SIR BANYAS

    Lay and burial of 2×13 km of 132kV power cable + 2x13km FO cable between Shuweihat and SIR BANIYAS (mainland to Island)
    Burial system : TM04 (trencher)
    Plus d’infos