Provision of personnel and equipment to carry out the trenching of 2 x 230 kV power cables in shallow water.

Location : Abu Ali – Saudi Arabia
Client : Mc Dermott Arabia Company Ltd

Product : Power Cable
Length (km): 2 x 5.9 km
Water depth (m) : 0 to 11
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1.3
Weight (kg/m) : 96
Diameter : 237 mm