Home » Projets » 2015 ABU ALI

2015 ABU ALI

Provision of personnel and equipment to carry out the trenching of 2 x 230 kV power cables in shallow water.

Location : Abu Ali – Saudi Arabia
Client : Mc Dermott Arabia Company Ltd

Product : Power Cable
Length (km): 2 x 5.9 km
Water depth (m) : 0 to 11
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1.3
Weight (kg/m) : 96
Diameter : 237 mm

Other projects

  • 2023 MARTINIQUE

    Installation of 2 new electrical links in the bay of Fort de France
    Burial system :
    Plus d’infos
  • 2003 IFA 2000 – CABLE 11 REPAIR

    500 MW HVDC Power cable repair.
    Burial system : MED1 (Dredge pump)
    Plus d’infos
  • 2011 ORMONDE WINDFARM

    Post Lay Inspection and Burial of 32 infield power cables.
    Burial system : ROVJET605 (jetting)
    Plus d’infos