Home » Projets » 2015 ABU ALI

2015 ABU ALI

Provision of personnel and equipment to carry out the trenching of 2 x 230 kV power cables in shallow water.

Location : Abu Ali – Saudi Arabia
Client : Mc Dermott Arabia Company Ltd

Product : Power Cable
Length (km): 2 x 5.9 km
Water depth (m) : 0 to 11
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1.3
Weight (kg/m) : 96
Diameter : 237 mm

Other projects

  • 2017 QUINTILLION ALASKA

    1 separate shore end. 16 km cable installation with laying and burial.
    Burial system : ESV12 (vibrating plough)
    Plus d’infos
  • 2024 2 AFRICA

    PLIB in various West African countries
    Burial system :
    Plus d’infos
  • 2021 AMITIE

    Separate shore ends in La Grigne. HDD Pulling, Laying and burial of 2.3 km of fibre optic cable.
    Burial system :
    Plus d’infos