Home » Projets » 2015 FITZROY Port Hedland

2015 FITZROY Port Hedland

2 separate shore ends. Double 44km cable installation with simultaneous laying and trenching (both cables in the same trench) and surface lay with a minimum 5m separation between both cables. Installation of articulated pipes.

Location : Port Hedland / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable
Length (km): 2 x 44
Water depth (m) : up to 17 m
Vessel : Barge
Burial system : TM04 (trenching) + EBJ (jetting)
Burial depth (m) : 0.5
Weight (kg/m) : 3.5
Diameter : 35

Other projects

  • 2010 MANIFA

    Provison of technical and engineering services / Cable laying and trenching services.
    Burial system : TM04 (Trencher)
    Plus d’infos
  • 2022 2 AFRICA MARSEILLE

    2 x Direct landing in Marseilles. Shell installation
    Burial system :
    Plus d’infos
  • 1999 DCN TOULON

    Power and composite cables inside miltary harbour.
    Burial system : N.A.
    Plus d’infos