1 separate shore end. 3km cable installation with laying and post burial.  Installation of articulated pipes.

Location : Darwin / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable
Length (km): 3
Water depth (m) : up to 20 m
Vessel : Barge
Burial system : TO Mobile (jetting)
Burial depth (m) : 2
Weight (kg/m) : 3.5
Diameter (mm) : 35