Home » Projets » 2017 QUINTILLION ALASKA

2017 QUINTILLION ALASKA

1 separate shore end. 16 km cable installation with laying and burial.

Location : Prudhoe Bay/ Alaska
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable 
Length (km): 16
Water depth (m) : up to 15 m
Vessel : Barge
Burial system : ESV12 (Vibrating plough)
Burial depth (m) : 2
Weight (kg/m) : 4
Diameter (mm) : 37.5

Other projects

  • 2018 TRIANEL BORKUM II OWF

    Provision of personnel and equipment to carry out the post lay burial of 18 infield power cables.
    Burial system : ROVJET 1210 (jetting)
    Plus d’infos
  • 2020 Partnership with UXO Control

    Offshore campaign to identify and eliminate unexposed ammunition (UXO) on the site of the Saint-Brieuc wind farm
    Burial system : TRITON XLX200HP and ROV C 113
    Plus d’infos
  • 2020 JOHAN SVERDRUP 2

    Post lay burial of seismic fibre optic cable in Johan Sverdrup Field (Equinor)
    Burial system : ROVJET 1206
    Plus d’infos