Home » Projets » 2021 AMITIE

2021 AMITIE

Separate shore ends in La Grigne. HDD Pulling, Laying and burial of 2.3 km of fibre optic cable.

Place: La Grigne (France)
Client : Alcatel Submarine Networks (ASN)

Product : fibre optic cable
Length:2.3 km
Depth: Up to 15 m
Ship: Barge
Burial system: Mass Flow Excavation
Burial depth: 1 m

Period: Sept 2021

Other projects

  • 2021 YUNLIN OWF

    Provision of personnel and equipment to carry out the post lay burial of infield array cables.
    Burial system :
    Plus d’infos
  • 2025 CSN-1 COLOMBIA

    Separate landing in Barranquilla. Laying and post-wiring of 8.5 km of fiber optic cable, Installation of grounding system
    Burial system :
    Plus d’infos
  • 2002 FLAG SOUTH PLIB

    PLIB works on telecommunication fibre optic cable.
    Burial system : MED1 (Dredge pump)
    Plus d’infos