2021 AMITIE

Separate shore ends in La Grigne. HDD Pulling, Laying and burial of 2.3 km of fibre optic cable.

Place: La Grigne (France)
Client : Alcatel Submarine Networks (ASN)

Product : fibre optic cable
Length:2.3 km
Depth: Up to 15 m
Ship: Barge
Burial system: Mass Flow Excavation
Burial depth: 1 m

Period: Sept 2021