2012 THORNTON BANK

Post-Lay burial of the export power cable of the Thornton Bank Offshore Windfarm.

Location : Thornton Bank Windfarm, Ostende (BELGIUM)
Client : VSMC / C-POWER

Product : Power Cable 
Length (km): 36
Water depth (m) : 0 to 26
Vessel : DP Vessel + Barge
Burial system : ROVJET605 + ROVJET806 (jetting)
Burial depth (m) : 1.5 
Weight (kg/m) : max 44
Diameter : max 234 mm

Other projects

  • 2025 MARJAN GOSP 4

    Supply of personnel and trenching services for two separate 230 kV composite submarine cable burial services on the Marjan field as part of the Marjan Oil-Gas Separation Plant No. 4 (MRJN GOSP 4) development project.
    Burial system :
    Plus d’infos
  • 2017 BEATRICE OWF

    Provision of personnel and equipment to carry out the post lay burial of 56 infield power cables.
    Burial system : ROVJET 1210 (jetting)
    Plus d’infos
  • 2024 DOGGER BANK B

    Supply of trenching support services, including personnel and equipment on board a dedicated trenching support vessel (TSV), for the Dogger Bank offshore wind farm inter-turbine cable installation and protection project.
    Burial system :
    Plus d’infos