Home » Projets » 2008 PERENCO RDC

2008 PERENCO RDC

Cable laying and burial between mainland and platforms. Barge operating for pipe laying + special liftings + J-tube pullin.

Location : Democratic Republic of the Congo
Client : PERENCO

Length (km): 22
Water depth (m) : 20
Vessel : Barge
Burial system : EBJ 04 (jetting)
Burial depth (m) : 0,8
Product : Power Cable
Weight (kg/m) : 7
Diameter : 96 mm

Other projects

  • 2001 CROSSING TAT 14

    PLIB works on telecom FO cable crossings with RTE / NGC power cables
    Burial system : MED1 (Dredge pump)
    Plus d’infos
  • 2003 IFA 2000 – CABLE 11 REPAIR

    500 MW HVDC Power cable repair.
    Burial system : MED1 (Dredge pump)
    Plus d’infos
  • 2024 DOGGER BANK B

    Supply of trenching support services, including personnel and equipment on board a dedicated trenching support vessel (TSV), for the Dogger Bank offshore wind farm inter-turbine cable installation and protection project.
    Burial system :
    Plus d’infos