2014 GÉOCEAN BÉNIN

Laying of 14km of power cable between mainland and a platform. Burial in shallow water from 8m to the beach.
Installation of articulated pipes.

Location : Bénin
Client : GEOCEAN

Length (km): 14 
Water depth (m) : 0 to 26
Vessel : Barge
Burial system : EBJ (jetting)
Burial depth (m) : 1.5
Product : Power cable
Weight (kg/m) : 30
Diameter : 108 mm