Home » Projets » 2003 ILE D’YEU

2003 ILE D’YEU

Mainland to island / Shore ends / Laying and burial of 20 kV pc

Location : FRANCE – ILE D’YEU/SAINT JEAN DE MONTS
Client : NEXANS

Length (km): 18
Water depth (m) : 8
Vessel : Barge
Burial system : N.A.
Burial depth (m) : 1,8
Product : Power Cable
Weight (kg/m) : 28
Diameter : 111 mm

Other projects

  • 2008 DELMA

    Post trenching of 2 power cables between Shuwaihat (mainland) and Delma Island. Installation of articulated pipes.
    Burial system : TM04 (Trencher)
    Plus d’infos
  • 2023 CFXD

    Assistance to laying, PLIB
    Burial system :
    Plus d’infos
  • 2000 PEC / LEVEL 3/ FLUTE

    PLIB works on telecom fibre optic cable crossings.
    Burial system : MED 1: Dredge pump / jetting tool
    Plus d’infos