Home » Projets » 2003 ILE D’YEU

2003 ILE D’YEU

Mainland to island / Shore ends / Laying and burial of 20 kV pc

Location : FRANCE – ILE D’YEU/SAINT JEAN DE MONTS
Client : NEXANS

Length (km): 18
Water depth (m) : 8
Vessel : Barge
Burial system : N.A.
Burial depth (m) : 1,8
Product : Power Cable
Weight (kg/m) : 28
Diameter : 111 mm