2014 BUTENDIEK

Provision of personnel and equipment to carry out the post burial of 86 infield power cables.

Location : BUTENDIEK Offshore Windfarm / German North Sea
Client : VBMS

Product : Power Cable 
Length (km): 81
Water depth (m) : up to 22 m
Vessel : DP Vessel
Burial system : ROVJET806 (jetting)
Burial depth (m) : 1
Weight (kg/m) : –
Diameter : 

Other projects

  • 2013 VISCAS SIR BANYAS

    Lay and burial of 2×13 km of 132kV power cable + 2x13km FO cable between Shuweihat and SIR BANIYAS (mainland to Island)
    Burial system : TM04 (trencher)
    Plus d’infos
  • 2023 BLUE GENOA

    2 x Direct landings at Genoa in a directional borehole. Shell installation
    Burial system :
    Plus d’infos
  • 2020 Dunant

    Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.
    Burial system : TO Mobile (jetting)
    Plus d’infos