Home » Projets » 2022 GRACE HOPPER

2022 GRACE HOPPER

Separate landing in a directional borehole. Simultaneous installation and beaming with mechanical trencher

Location: New York USA, Smith Point
Customer: SUBCOM

Length (km): 8.5 km
Water depth (m) :
Vessel: VOS STAR
Beaching system: TMO 4
Beaching depth (m): 1.35 m
Product : Fiber optic cable
cable type: ø37mm

Other projects

  • 2025 MARJAN GOSP 4

    Supply of personnel and trenching services for two separate 230 kV composite submarine cable burial services on the Marjan field as part of the Marjan Oil-Gas Separation Plant No. 4 (MRJN GOSP 4) development project.
    Burial system :
    Plus d’infos
  • 2008 DELMA

    Post trenching of 2 power cables between Shuwaihat (mainland) and Delma Island. Installation of articulated pipes.
    Burial system : TM04 (Trencher)
    Plus d’infos
  • 2023 GHANA

    Separate landing in Accra. Laying and post-wiring of 4.9 km of fiber optic cable
    Burial system :