Home » Projets » 2015 QUIBERON BELLE ISLE 4

2015 QUIBERON BELLE ISLE 4

Laying of 14.5 km of hybrid cable between Quiberon (mainland) and Belle Isle.
Location : Quiberon – Belle Isle  (Brittany)
Client : ERDF
Length (km): 14.5
Water depth (m) : 0 to 25
Vessel : DP vessel
Burial system : N.A.
Burial depth (m) : N.A.
Product : Hybrid Cable (Power + FO)
Weight (kg/m) : 29
Diameter : 122 mm

Other projects

  • 1999 ELGIN FRANKLIN

    Platform to platform / Composite power and communication cable + 1 composite power / communication cable + 1 umbilical.
    Burial system : CASTOR 2 (Trencher)
    Plus d’infos
  • 2022 2/AFRICA GENES

    2 x Direct landings in Genoa. Installation of shells and post-sinking. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2004 SIR BANIYAS

    Lay and burial of 2×9 km of 33kV power cable between Jebel Dhanna and SIR BANIYAS (mainland to Island)
    Burial system : TM03 (Trencher)
    Plus d’infos