Page 8 of 9

2001 ULYSSE
Recover of existing cable (5 km), simultaneous lay and burial work (ESV12), PLIB work of joints (MED 1 and diver pump).
Burial system : MED1 (Dredge pump) - ESV12 (Plough)
Plus d'infos
2001 SAT 3
DOUALA and LIBREVILLE shore ends / Laying and burial of FO cable
Burial system : TJV05 - TJV04 (Jetting) + ESV12 (Plough)
Plus d'infos
2001 APOLLO UK SHORE END
Cable lay and burial BUDE shore end (UK).
Burial system : TJV04 (Jetting)
Plus d'infos
2000 VNF LILLE
Along river – canal / 1 telecommunication fibre optic cable.
Burial system : Machine LD CABLE : Towed plough
Plus d'infos
2000 PEC / LEVEL 3/ FLUTE
PLIB works on telecom fibre optic cable crossings.
Burial system : MED 1: Dredge pump / jetting tool
Plus d'infos
2000 Dumpton Gap – Level 3
Remedial work : Lay and simultaneous burial of fibre optic cable.
Burial system : ESV11 (Plough)
Plus d'infos
2000 FLAG ATLANTIC 1
3 separate shore end installations as part of the FLAG Atlantic 1 telecommunication cable system.
Burial system : MED1 (Jetting) and ESV11 (Plough)
Plus d'infos
1999 ELGIN FRANKLIN
Platform to platform / Composite power and communication cable + 1 composite power / communication cable + 1 umbilical.
Burial system : CASTOR 2 (Trencher)
Plus d'infos
1999 CIRCE
Cable deburial / reburial and cable loop burial on CIRCE fibre optic cable system.
Burial system : MED1 (Dredge pump) - CASTOR (Trencher)
Plus d'infos
1998-1999 VNF PARIS
Along river / Laying and burial of 3 multiple FO cables laid in one go
Burial system : ESV 07 / ESV11 (Plough)
Plus d'infos
1999 DCN TOULON
Power and composite cables inside miltary harbour.
Burial system : N.A.
Plus d'infos
1998 BELIZE
Main land to island / 34.5 kV power extension.
Burial system : TJV04 (Jetting)
Plus d'infos