2026 SMW-6
Direct landing in Yanbu (Saudi Arabia) and installation of articulated pipes on 0.7 km of fiber optic cable.
-

2026 Lumalink
Mobilization of the DP barge in Panama, followed by towed transit to Cayenne (French Guiana). Separate shore-end landing, simultaneous laying and burial of 15 km of fiber optic cable.
-

2026 CSN-1 (USA)
Mobilization of the DP vessel Sarah Bordelon in Houma (Louisiana), followed by transit to Florida. Separate shore landing at Bonita Springs, lay and post-lay burial of 30 km of fiber optic cable, followed by a PLIB over approximately 100 km.
-

2026 CSN-1 (Ecuador)
Direct shore landing at Anconcito (Ecuador), shell laying and post-lay burial of 2.7 km of fiber optic cable.
-

2025 ZULUF
Supply of personnel and trenching services for the burial of a 230 kV composite submarine cable in the Zuluf field
-
-

2025 NOY YEU NOIRMOUTIER WINDFARM
EPCI contract for the supply, installation and protection of inter-wind turbine cables for the YEU NOIRMOUTIER offshore wind farm.
-
2025 NOY YEU NOIRMOUTIER WINDFARM
EPCI contract for the supply, installation and protection of inter-wind turbine cables for the YEU NOIRMOUTIER offshore wind farm.
-

2025 MARJAN GOSP 4
Supply of personnel and trenching services for two separate 230 kV composite submarine cable burial services on the Marjan field as part of the Marjan Oil-Gas Separation Plant No. 4 (MRJN GOSP 4) development project.
-
-

2025 CSN-1 PANAMA
Separate landing at Costa del Este. Laying and post-wiring of 11.8 km of fiber optic cable
-

2025 CSN-1 COLOMBIA
Separate landing in Barranquilla. Laying and post-wiring of 8.5 km of fiber optic cable, Installation of grounding system
Projects